Tips and notices when install and operate ball mill

Date:2013-07-17 00:27:23 ?? Source:Clirik

1.Installation plan is designed according to user's basic engineering, users should install the   machine according its direction, location and space.
2. Adjust the horizontal level and the level material cylinder bottom plane is not more than 1.5/1000
3. The validity of processing the anti rust and anti oil is 12 months.
4. The accepted tolerance of the two bearing block is 5 mm, and the charging level should be higher than the discharging level.    
5.The gap between the small gear wheel and the big gear wheel is 1.7245mm.
6.Add 20%~30% steel ball and material on the load test after the succes un-load test.

Previous:Comparison Between the Grate Ball Mills and Overflow Type Ball Mills

Next:From —air pollution cuts life expectancy in north China by 5.5 years, see ball mill manufacturer in

Shanghai Clirik Machinery Co.,Ltd 2013-2016 all rights reserved. Tel:0086-21-20236178 Fax:0086-21-58974855 Address:No.19Fuqing Rd,Shanghai